Blanding Boulevard (State Road 21) Widening

Affected Areas
Roads: State Road 21
Counties: Clay
Cities: Orange Park
Overview
Project Began: September 2009
Expected Completion: Spring 2011
Project Description

Adding lanes from Old Jennings Road to Knight Boxx Road (1.2 miles). Russell Engineering, Inc., of Fort Lauderdale began Sept. 18, 2009 and should finish in 570 days (Spring of 2011) at a cost of $5,463,246.40. Sheldon Cash of Eisman & Russo is CEI project managers (904-272-0299).


For More Information Contact:
Mike Goldman - 800-207-8236